The Building Expansion Teams met this past week to continue their work on finalizing the plans for the building project. The current timeline of the project is to have the finished drawings by June 1, followed by a pre-bid conference with the General Contractors who have been invited to bid on the project. The bids will be due back by June 21, and the church will have up to 30 days to make a decision. Once the contractor is selected and final approval is given, the ten-month construction process will begin.
As always, if you have any questions or comments about the building project, please contact any member of the Building Expansion Teams or leave your comments on the wesbite.